Kelantan
This project is a water treatment plant for the provision of water to the communities in the surrounding area of Alor Kampung Telok. It was completed in April 2022.
In Pantau Projek, transparency is assessed based on 39 data points covering basic Project Identification as well as the phases of Preparation, Procurement, Implementation, and Completion. Data is only considered publicly available if it can be obtained online from a credible source.
An example of a state government or project owner website: www.mbiselangor.com
Available on State Govt and Project Owner website
For example, online news articles or social media postings
Available on 3rd party website
The information is not accessible in any online platform
Not available on any website
Available on State Govt and Project Owner website
17
Available on State Govt and Project Owner website
4
Not available on any website
18
Project Identification
Project owner | Ministry of Environment and Water (KASA) |
Sector, subsector | Utilities (Water) |
Project name | Projek Loji Rawatan Air Kampung Telok (Kampung Telok Water Treatment Plant) |
Project location | Jalan Taman Teluk Perdana, Kampung Telok, Kota Bharu, Kelantan |
Purpose | Provision of clean water |
Project description | Installation of a water treatment plant in Kampung Telok, Jajahan Kota Bharu, Kelantan (Design and Build) |
Project Preparation
Project scope (main output) | Water treatment plant |
Environmental impact | The information was not available online at the time of assessment. |
Land and settlement impact | The information was not available online at the time of assessment. |
Contact details | Ibu Pejabat Air Kelantan Sdn. Bhd. Tingkat 1, Bangunan Perbadanan Menteri Besar Kelantan, Lot 2 & 257, Jalan Kuala Krai, 15050 Kota Bharu, Kelantan Darul Naim |
Funding sources | Ministry of Environment and Water (KASA) |
Project budget | The information was not available online at the time of assessment. |
Project budget approval date | 16 June 2015 |
Tender Management
Procuring entity | Air Kelantan Sdn Bhd |
Procuring entity contact details | Air Kelantan Sdn. Bhd. Tingkat 1, Bangunan Perbadanan Menteri Besar Kelantan, Lot 2 & 257, Jalan Kuala Krai, 15050 Kota Bharu, Kelantan Darul Naim |
Procurement process | Open Tender |
Contract type | Design and Build |
Contract status (current) | Currently Closed |
Number of firms tendering | The information was not available online at the time of assessment. |
Cost estimate | The information was not available online at the time of assessment. |
Contract administration entity | Air Kelantan Sdn Bhd |
Contract title | MEMBINA LOJI RAWATAN AIR KG. TELOK, JAJAHAN KOTA BHARU, KELANTAN (REKA DAN BINA). |
Contract firm(s) | The information was not available online at the time of assessment. |
Contract price | The information was not available online at the time of assessment. |
Contract scope of work | The information was not available online at the time of assessment. |
Contract start date | The information was not available online at the time of assessment. |
Contract duration | The information was not available online at the time of assessment. |
Implementation
Variation to contract price | The information was not available online at the time of assessment. |
Escalation of contract price | The information was not available online at the time of assessment. |
Variation to contract duration | The information was not available online at the time of assessment. |
Variation to contract scope | The information was not available online at the time of assessment. |
Reasons for price changes | The information was not available online at the time of assessment. |
Reasons for scope & duration changes | The information was not available online at the time of assessment. |
Project Completion
Project status (current) | Completed |
Completion cost (projected) | RM48,229,508.06 |
Completion date (projected) | 4/1/2022 |
Scope at completion | The scope at completion is to produce 30 million liter of clean water per day. Project failed to produce the volume of treated water. |
Reasons for project changes | The information was not available online at the time of assessment. |
Reference to audit and evaluation reports | The information was not available online at the time of assessment. |