Sarawak
This project presents the New Sarawak Museum with exhibition spaces, commercial lots, function rooms and auditorium spaces. Consisting of 2 new buildings, the Borneo Cultures Museum and Annexe Office Building were officially completed in January 2020.
In Pantau Projek, transparency is assessed based on 39 data points covering basic Project Identification as well as the phases of Preparation, Procurement, Implementation, and Completion. Data is only considered publicly available if it can be obtained online from a credible source.
An example of a state government or project owner website: www.mbiselangor.com
Available on State Govt and Project Owner website
For example, online news articles or social media postings
Available on 3rd party website
The information is not accessible in any online platform
Not available on any website
Available on State Govt and Project Owner website
4
Available on State Govt and Project Owner website
18
Not available on any website
17
Project Identification
Project owner | Jabatan Muzium Sarawak |
Sector, subsector | Tourism, Arts & Culture |
Project name | Borneo Cultural Museum |
Project location | Jalan Tun Abang Haji Openg, 93400, Kuching, Sarawak |
Purpose | The new facilities will ensure that the Sarawak heritage, in the form of a wide array of collections, is safely and securely stored, preserved, documented, researched and well exhibited, according to the latest standards by the International Council of Museums. |
Project description | The new five-storey Sarawak Museum building consists of exhibition gallery spaces on Levels 2 to 5, flanking a central atrium on both wings. Level 1 houses commercial lots, a café, function rooms and auditorium spaces, which support and complement the temporary exhibition gallery. |
Project Preparation
Project scope (main output) | Gross Floor Area: Approximately 31,000 square metres Building Height Main: 5 storeys; 42.9 metres Annex: 3 storeys; 19.7 metres |
Environmental impact | The information was not available online at the time of assessment. |
Land and settlement impact | The information was not available online at the time of assessment. |
Contact details | Sarawak Museum Department Jalan P Ramlee 93400, Kuching, Sarawak Tel Hq: +6082-548181 Fax: +082-548282 Email: museum@sarawak.gov.my |
Funding sources | Sarawak State Government |
Project budget | RM308million + RM28million for conservation of existing museum building |
Project budget approval date | Cahya Mata Sarawak Berhad website: budget approved on 14th April 2015 |
Tender Management
Procuring entity | Cahya Mata Sarawak Bhd (CMSB) |
Procuring entity contact details | Cahya Mata Sarawak, Level 6, Wisma Mahmud, Jalan Sungai Sarawak, 93100 Kuching, Sarawak, Malaysia +60 82 238 888 +60 82 333 828 www@cmsb.my |
Procurement process | Direct Award – PPES Works (Sarawak) Sdn Bhd signed a Design & Build and negotiated contract with the Sarawak State Government for the proposed Sarawak Museum Campus & Heritage Trail in Kuching. |
Contract type | Design and Build and Negotiated Contract with the Sarawak State Government |
Contract status (current) | Closed (Project complete) |
Number of firms tendering | The information was not available online at the time of assessment. |
Cost estimate | RM 308 million |
Contract administration entity | PPES Works (Sarawak) Sdn Bhd, a subsidiary of CMS Works Sdn Bhd |
Contract title | The information was not available online at the time of assessment. |
Contract firm(s) | PPES Works (Sarawak) Sdn Bhd, a subsidiary of CMS Works Sdn Bhd |
Contract price | RM 308 million |
Contract scope of work | The contract between the Sarawak State Government/ Jabatan Muzium Sarawak and CMB Sdn Bhd |
Contract start date | The information was not available online at the time of assessment. |
Contract duration | 5 years (2015-2020) |
Implementation
Variation to contract price | No official statement or reports on contract price variation. |
Escalation of contract price | The information was not available online at the time of assessment. |
Variation to contract duration | “The new Sarawak Museum Complex, handed over to the Public Works Department (JKR) Sarawak and Museum Department Sarawak” according to Borneo Post dated 9/8/2019. |
Variation to contract scope | The information was not available online at the time of assessment. |
Reasons for price changes | The information was not available online at the time of assessment. |
Reasons for scope & duration changes | The information was not available online at the time of assessment. |
Project Completion
Project status (current) | Completed: handed over to JKR & Sarawak Museum on 8/8/2019 |
Completion cost (projected) | RM 323 million |
Completion date (projected) | January 2020 |
Scope at completion | The information was not available online at the time of assessment. |
Reasons for project changes | The information was not available online at the time of assessment. |
Reference to audit and evaluation reports | The information was not available online at the time of assessment. |