Terengganu
This project is South East Asia’s first tower drawbridge. It was officially launched and open for use in 2019.
In Pantau Projek, transparency is assessed based on 39 data points covering basic Project Identification as well as the phases of Preparation, Procurement, Implementation, and Completion. Data is only considered publicly available if it can be obtained online from a credible source.
An example of a state government or project owner website: www.mbiselangor.com
Available on State Govt and Project Owner website
For example, online news articles or social media postings
Available on 3rd party website
The information is not accessible in any online platform
Not available on any website
Available on State Govt and Project Owner website
16
Available on State Govt and Project Owner website
8
Not available on any website
15
Project Identification
Project owner | Terengganu State Government |
Sector, subsector | Tourism Transport/ Urban Development – Traffic |
Project name | Terengganu Drawbridge/ Jambatan Angkat Terengganu |
Project location | Mouth of Kuala Terengganu RIver, Terengganu, Malaysia. [postcode: 20000] |
Purpose |
|
Project description |
|
Project Preparation
Project scope (main output) |
|
Environmental impact | EIA carried out but unavailable online |
Land and settlement impact | Details not available online (EIA & other assessments carried out but not available online) |
Contact details | Tingkat 15 Wisma Darul Iman Kuala Terengganu, Terengganu, 20503 Malaysia webmaster@terengganu.gov.my |
Funding sources | Funded by Terengganu State Government |
Project budget | RM248 million |
Project budget approval date | The information is unavailable online at the time of assessment. |
Tender Management
Procuring entity | Wilayah Ekonomi Pantai Timur (ECER) |
Procuring entity contact details | ZELAN BERHAD (27676-V) 24th Floor, Wisma Zelan No. 1, Jalan Tasik Permaisuri 2, Bandar Tun Razak, Cheras, 56000 Kuala Lumpur, Malaysia Tel: +603 9173 9173 Fax: +603 9171 8191 Email: info@zelan.com.my GPS Coordinate: ( 3.09963,101.717933 ) |
Procurement process | Open Tender |
Contract type | The information is unavailable online at the time of assessment. |
Contract status (current) | Closed |
Number of firms tendering | The information is unavailable online at the time of assessment. |
Cost estimate | The information is unavailable online at the time of assessment. |
Contract administration entity | Wilayah Ekonomi Pantai Timur (ECER). |
Contract title | The proposed Construction and Completion of the Drawbridge Connecting Muara North and Muara South in Kuala Terengganu City Centre for the East Coast Economic Region Development Council (ECERDC) (IN/T14-020) |
Contract firm(s) | Zelan – Hasrat Sedaya Consortium |
Contract price | The contract value is RM 248,728,66 and won by Zelan-Hasrat Usaha Consoritum |
Contract scope of work | The information is unavailable online at the time of assessment. |
Contract start date | 13 August 2014 |
Contract duration | The contract duration is 135 weeks, commencing on the date for possession of the Site on 13 August 2014. However, due to improvisations, the works are still in progress and a new completion date will be determined soon. |
Implementation
Variation to contract price | The information is unavailable online at the time of assessment. |
Escalation of contract price | The information is unavailable online at the time of assessment. |
Variation to contract duration | The information is unavailable online at the time of assessment. |
Variation to contract scope | The information is unavailable online at the time of assessment. |
Reasons for price changes | The information is unavailable online at the time of assessment. |
Reasons for scope & duration changes | The information is unavailable online at the time of assessment. |
Project Completion
Project status (current) | Completed |
Completion cost (projected) | RM248 million |
Completion date (projected) | 3/14/2017 |
Scope at completion | Bridge is:
|
Reasons for project changes | In 2019, the bridge was still incomplete – at “99% completion”. No information available as to what caused the delay. |
Reference to audit and evaluation reports | The information is unavailable online at the time of assessment. |