Penang Undersea Tunnel

Pulau Pinang

Pulau Pinang

The Penang Undersea Tunnel is part of the Penang State Government initiative under the Penang Transport Master Plan. It plans to feature a tunnel connecting Butterworth and George Town in Penang. The project is currently on hold.

In Pantau Projek, transparency is assessed based on 39 data points covering basic Project Identification as well as the phases of Preparation, Procurement, Implementation, and Completion. Data is only considered publicly available if it can be obtained online from a credible source.

Available on State Govt and Project Owner website

Available on 3rd party website

Not available on any website

Project Identification

Project owner
The Penang Undersea Tunnel is part of the Penang State Government initiative under the Penang Transport Masterplan. The ultimate project owner is the Penang State Government.
Sector, subsector
Transport
Project name
Penang Undersea Tunnel
Project location
Penang – Butterworth (no exact name of the location yet can be found)
Purpose
To further enhance connectivity between the island and the mainland – the undersea tunnel and roads project was mooted by the Penang government to alleviate traffic on the first bridge and to cut down traffic at other congested corridors on the island.
Project description
The 7.2km undersea tunnel will connect George Town on Penang Island to Butterworth on the mainland and the three main highways comprising the 10.53km Tanjung Bungah-Teluk Bahang paired road, 5.7km Air Itam-Tun Dr Lim Chong Eu Expressway and 4.1km Gurney Drive-Tun Dr Lim Chong Eu Expressway paired roads.
Project scope (main output)
The information was unavailable at the time of the assessment.
Environmental impact
The information was unavailable at the time of the assessment. Feasibility study still under review.
Land and settlement impact
Information was not available online during the time of assessment. Feasibility study still under review.
Contact details
Paras 25, KOMTAR, 10503 Pulau Pinang
Tel : +604-2621957 / +604-2642020
Faks : +604-2634940
Emel : webmaster@penang.gov.my
Funding sources
Information was not available online during the time of assessment.
Project budget
Information was not available online during the time of assessment.
Project budget approval date
Information was not available online during the time of assessment.
Procuring entity
Penang State Government.
Procuring entity contact details
Paras 25, KOMTAR, 10503 Pulau Pinang
Tel : +604-2621957 / +604-2642020
Faks : +604-2634940
Emel : webmaster@penang.gov.my
Procurement process
The process began in 2011. Sixty companies (43 local and 17 international firms) took part in the pre-qualification briefing, but eventually, eight were qualified to participate in the request for proposal stage.

Finally, the bid was won by Consortium Zenith BUCG. The special purpose vehicle (SPV) was led by Beijing Urban Construction Group (BUCG) in collaboration with a few local firms.
Contract type
Construction
Contract status (current)
Closed – the bid was won by Consortium Zenith BUCG.
Number of firms tendering
Sixty companies, including 43 local and 17 international firms took part in the pre-qualification briefing, but eventually, only eight were invited for the Request for Proposal (RFP).
Cost estimate
Information was not available online during the time of assessment.
Contract administration entity
Information was not available online during the time of assessment.
Contract title
Information was not available online during the time of assessment.
Contract firm(s)
Information was not available online during the time of assessment.
Contract price
Information was not available online during the time of assessment.
Contract scope of work
Information was not available online during the time of assessment.
Contract start date
Information was not available online during the time of assessment.
Contract duration
Information was not available online during the time of assessment.
Variation to contract price
Information was not available online during the time of assessment.
Escalation of contract price
Information was not available online during the time of assessment.
Variation to contract duration
Information was not available online during the time of assessment.
Variation to contract scope
Information was not available online during the time of assessment.
Reasons for price changes
Information was not available online during the time of assessment.
Reasons for scope & duration changes
Information was not available online during the time of assessment.
Project status (current)
The project is currently on hold waiting to be reviewed.
Completion cost (projected)
RM 6.3 million
Completion date (projected)
Expected completion date is 2025.
Scope at completion
Information was not available online during the time of assessment.
Reasons for project changes
  • Delay in feasibility study (Completion date delayed from 2016 to December 2020)
  • The centre of graft allegations against former Penang chief minister Lim Guan Eng.
Reference to audit and evaluation reports
Information was not available online during the time of assessment.